Dear,
ECC6.0
Windows Server 2003
Oracle 10.0.2.4
Hard Disk- 1 TB free 400 GB.
RAM - 8GB
regards
Dear,
ECC6.0
Windows Server 2003
Oracle 10.0.2.4
Hard Disk- 1 TB free 400 GB.
RAM - 8GB
regards
now how is running SGEN?
how many processors and its Core?
Regards,
Now i am running DB statistics and let u know when it will complt.
Hi Santosh
1. Any Error message in SM21 log? any dumps in ST22?
2. After installed the SAP system have you define the memory parameters based on physical memory 8 Gb? refer the SAP Note 88416
Regards
SS
Hi Sriram,
Now its working good.
thanks
Regards
Santosh
Hi Jamil,
Thanks Its working good now.
Regards
Santosh
Dear All,
i am upgrading the ECC server from EHP 3 to EHP 6, starting shadow instance failed after DBCLONE phase completed, after read some blogs i have restarted the shadow and main instance, now both message server are not connecting so dispatcher got stopped. kindly help me to solve the issue.
Thanks in Advance
Regards
Sivakumar.TA
hello Rami
can you tell me if it is possible to download the Solution Builder?
Please send me the link. Many thanks.
Nick
Jason, we are facing that same issue... In our case attaching a document to a contract record (RECN transaction). We just applied Stack 14 to our ERP EHP6 installation, and updated the Kernel to 7.21.
Have you had any success in finding out what is causing this?
Any information will be helpful as we are running out of ideas here.
Thanks
Laurie McGinley
SAP Nature System Analyst
I'm sorry Laurie. We have not received any feedback on this issue. And it is still an issue on our upgrade landscape.
Ok. We will continue to research as well. Hopefully someone will chime in here with an answer!
Laurie
We will do the same here.
Hi ,
Can you please attach the SLog , ULog and ALog so that I could check the error in more detail ?
Thanks & Regards,
Ashish
Hi,
Please check the following KBAs which describe your issue :
1541124 - Importing of a Support Package or transporting a change request errors out: "object was repaired in this system"
1913676 - IMPORT_PROPER:Troubleshooting guide for Support Package / Add-Ons Installations errors during the main import in SPAM or SAINT
Regards,
Rimjhim
Hi Sivakumar,
Could you please attach us the latest 10 traces from the work folder of shadow system.
Regards,
Anand.
HI,
I have facing a issue regarding transfer functional area line items records, in cost center, cost element & G/L master data level the change has been made with the message control filed, but the old line items record has not transfer in new functional area. does it possible ??
thanks,
Regards.
Junaid Shera
Hello Team,
We upgrading the ECC6.0 EHP1 to EHP7, We are in checks phase. While starting the upgrade we provided one password for SYSTEM in SUM tool. Then due to some reasons we changed the password of SYSTEM user password. In the PREP_SPACECAL/TABSPC_PREP phase we are getting the error saying that brconnect exit with 3. In the log file(ORA_COLLSPCSTAT.SAV) we checked that SYSTEM user ID and password is wrong logon denied.
We are provided the changed password but SUM is not taking. Again and again we are getting the same error. We tried to change the password with SQLPLUS and brconnect, but no luck.
Regards,
Patan Thavaheer.
Hello Patan,
If you are at the initial phase, please stop the upgrade, change the password at DB level and then Restart SUM.
Hope this helps!
Amit
Hello Siva,
Did you try to start the shadow system manually? What command did you use?
What is the current state of the system, is your Source system up now?
Please let us know!
Amit